Complete commercial fit-out of a new retail space, delivered on schedule despite national supply-chain disruptions.
Long-lead HVAC equipment was delayed six weeks. The tenant had a hard grand-opening date tied to a marketing campaign.
We restructured the critical path to front-load millwork, flooring, and finishes while the HVAC was in transit, then sequenced the final rough-in on nights and weekends.
Timeline management
Weekly owner meetings, daily foreman huddles, and a shared Monday-morning schedule update kept every trade moving on the same plan.
Finish work
Epoxy floors, custom steel display fixtures, and a fully conditioned mezzanine office — all in a compressed thirty-day final push.